Home

This document is a cache from http://www.utexas.edu/its/campus-security/files/280000%20Electronic%20Security%20Guide%20Specification.pdf


ELECTRONIC SECURITY SYSTEM DESIGN, CONSTRUCTION AND ...

Document source : www.utexas.edu


28 00 00 ELECTRONIC SAFETY AND SECURITY
June 16, 2009
33
APPENDIX B
CRITICAL SECURITY MILESTONES BY CALENDAR DAYS PRIOR TO SUBSTANTIAL COMPLETION
Column A
Column E
DURATION
DAYS before
IN DAYS
CRITICAL MILESTONES
PREREQUISITE START CONDITIONS
SUBSTANTIAL
Wire and cable installation.
1. Pathway, conduit and cable tray installation is
complete.
98
Access control, intrusion
detection & CCTV system
headend equipment
installation.
1. Equipment rooms are complete.
2. Plywood is on the wall for wall mounted enclosures.
3. Equipment rack is installed for DVR.
4. Power is available.
5. Ground bar is installed.
70
Field device wiring &
termination for access
control.
1. Door, frame and hardware are installed and functional.
70
Wall mounted devices
installation.
1. Paint and finish work on walls is complete.
63
Equipment Start Up
1. MDF completed and ITS has installed OSP feeder
cables.
2. Voice and data horizontal cabling must be installed,
tested and labled.
3. Riser cables for connecting network switches to the
gateway must be installed, tested and labled.
4. Network rooms that need switches for security must be
complete with grounding, HVAC and locks on the door.
ITS Networking will then install switch.
5. Pre-functional test requirements complete and
approved by ITS.
6. Operational field testing completed with ITS.
56
Functional Test
1. Equipment start up requirments are complete including
testing with ITS security operations.
21
Integrated System Test
1. Fire alarm system is complete and fire alarm relay
interface to the lock power supplies is installed.
2. Elevator controls are functional and fully operational.
7

INSTRUCTIONS:
Column A: Enter calendar days required to complete this activity
Column E: Enter calendar days prior to SC this prerequisite activity must be completed





















Summary :

28 00 00 ELECTRONIC SAFETY AND SECURITY June 16, 2009 33 APPENDIX B CRITICAL SECURITY MILESTONES BY CALENDAR DAYS PRIOR TO SUBSTANTIAL COMPLETION Column A Column E DURATION DAYS before IN DAYS CRITICAL MILESTONES PREREQUISITE START CONDITIONS SUBSTANTIAL Wire and cable installation.


Tags : complete,installed,days,equipment,column,installation,security,start,test,calendar,system,completed,wall





Terms    |    Link pdf-search-files.com    |    Site Map
   |    Content Removal Notice   
   |    Contact   

All books are the property of their respective owners.
Please respect the publisher and the author for their creations if their books copyrighted