3.4.5.3 Test
Per approved test procedures and under the direction of the Contractor's
Commissioning Team Leader, the Commissioning Team shall perform a
Performance Verification Test of the installed Access Control Point Control
System. The PVT shall demonstrate that the system complies with the
requirements specified herein. Where possible, the PVT shall be conducted
during regular daytime working hours on weekdays. At the successful
completion of each test in the PVT, appropriate Commissioning Team Members
shall sign the completed test procedure to certify that the test was
successful.
3.4.5.4 Test Report
Within seven (7) days of successful completion of the PVT, the Contractor's
Commissioning Team Leader shall submit a Test Report to the Contracting
Officer documenting the results of the test. The Test Report shall include
the results of all test procedures showing all commands, stimuli, and
responses to demonstrate compliance with the contract requirements. The
Test Report shall also include a certification from each Commissioning Team
member that the tests were successful. The Contracting Officer will notify
the Contractor, within 7 days of receipt of the Test Report, whether the
Test Report is approved. If disapproved, the Contracting Officer will note
the specific procedures that are disapproved; retest those procedures. Do
not start the Endurance Test until the PVT Test Report is approved by the
Contracting Officer.
[3.4.5.5 Opposite Season Test
**************************************************************************
NOTE: If temperature lows at the site dip to below
freezing in the winter time, specify an opposite
season test. If the initial pvt test is done in the
winter, specify an opposite season test in the
summer. If the initial pvt is done in the spring,
summer, or fall; specify an opposite season test in
the winter.
**************************************************************************
Coordinate with the Commissioning Team to conduct an opposite season PVT in
the [summer] [winter] months. All PVT tests and test reports required for
the initial PVT shall be required for the opposite season PVT.
]3.4.6 Endurance Test
3.4.6.1 General
In accordance with the Group IV Technical Data Package, the Contractor's
Commissioning Team Leader shall submit a Test Plan including a schedule,
test description, list of personnel required to conduct the test, and a
list of all data to collect and observances to be made in order to
demonstrate system reliability and operability of the completed Access
Control Point Control System. The Endurance Test shall be conducted in
phases as specified. The Endurance Test shall not be started until the
Contractor notifies the Contracting Officer, in writing, that training as
specified has been completed and that the correction of all outstanding
deficiencies has been satisfactorily completed. The Contracting Officer
may terminate the testing at any time the system fails to perform as
specified. Upon termination of testing by the Contracting Officer or by
SECTION 34 41 26.00 10 Page 50