the Contractor, commence an assessment period as described for Phase II
below.
3.4.6.2 Phase I Testing
The test shall be conducted 24 hours per day for 15 consecutive calendar
days, including holidays, and the system shall operate as specified. Make
no repairs during this phase of testing unless authorized by the
Contracting Officer in writing. If the system experiences no failures
during Phase I testing, the Contractor may proceed directly to Phase III
testing after receipt of written permission from the Contracting Officer.
3.4.6.3 Phase II Assessment
After the conclusion of Phase I, identify all failures, determine causes of
all failures, repair all failures, and deliver a written report to the
Contracting Officer. The report shall explain in detail the nature of each
failure, corrective action taken, results of tests performed, and shall
recommend the point at which testing should be resumed. After delivering
the written report, convene a test review meeting at the jobsite to present
the results and recommendations to the Contracting Officer. The meeting
shall not be scheduled earlier than 5 business days after receipt of the
report by the Contracting Officer. As a part of this test review meeting,
demonstrate that all failures have been corrected by performing appropriate
portions of the performance verification test. Based on the Contractor's
report and the test review meeting, the Contracting Officer will determine
the restart date, or may require that Phase I be repeated. If the retest
is completed without any failures, proceed directly to Phase III testing
after receipt of written permission from the Contracting Officer.
3.4.6.4 Phase III Testing
The test shall be conducted 24 hours per day for 15 consecutive calendar
days, including holidays, and the system shall operate as specified. Make
no repairs during this phase of testing unless authorized by the
Contracting Officer in writing.
3.4.6.5 Phase IV Assessment
After the conclusion of Phase III, identify all failures, determine causes
of failures, repair failures, and deliver a written report to the
Contracting Officer. The report shall explain in detail the nature of each
failure, corrective action taken, results of tests performed, and shall
recommend the point at which testing should be resumed. After delivering
the written report, convene a test review meeting at the jobsite to present
the results and recommendations to the Contracting Officer. The meeting
shall not be scheduled earlier than 5 business days after receipt of the
report by the Contracting Officer. As a part of this test review meeting,
demonstrate that all failures have been corrected by repeating appropriate
portions of the performance verification test. Based on the Contractor's
report and the test review meeting, the Contracting Officer will determine
the restart date, and may require that Phase III be repeated. Do not
commence any required retesting until after receipt of written notification
by Contracting Officer. After the conclusion of any retesting which the
Contracting Officer may require, the Phase IV assessment shall be repeated
as if Phase III had just been completed.